|
Managing
Growth
Client:
A processing plant with 1,000+ employees.
Situation:
The addition of several very large accounts meant that suddenly,
our client needed to hire 400 full-time workers within four months.
During the hiring process, they would require all of their employees
to work mandatory overtime in order to meet the production goals.
Assessment:
At first, the mandatory overtime worked well. Employees liked the
extra money, and management was able to meet production goals. Eventually,
employees began to "burn out" working seven days a week
and started to call in sick for their scheduled weekend overtime.
Failing to supply the promised amounts of product put the client's
contracts at risk; so in an effort to fix the situation quickly,
management decided to pay the employees an additional bonus of one
hundred dollars for each day they worked on the weekend, in addition
to time and a half for Saturdays and double time for Sundays. Paying
all the overtime and added bonuses caused production costs to increase
dramatically.
Strategy:
Life Style was brought in to meet two objectives:
1.
Hire the 400 people necessary to fill the full-time permanent
openings created by the increase in business. These workers would
be needed in increments starting immediately, spread over a four
month period.
2.
Design a strategy to keep staff at appropriate levels, while at
the same time being more efficient and cost-conscious.
Result:
We immediately developed a multifaceted customized recruiting program
to address the need for the 400 additional employees. Our objective
was to hit 20% of the goal in the first month, 35% of the goal in
the second and third months, and the remaining 10%, plus an allowance
for attrition, in the final month. Using the recruiting plan we
developed, we were able to reach 100% of the targeted levels by
the middle of the third month.
To
address the short-term immediate needs on the weekends, we designed
a weekend-only staffing program. We developed a workforce that would
take advantage of "moonlighters" or people with second
jobs. We allowed these staffers to choose their own schedule - work
one weekend day or two. We set a pay rate higher than the weekday
rate, but lower than the overtime and double rates. We were then
able to add the necessary people to meet the production goals each
week, at a cost 23% lower than previous efforts, resulting in a
savings of $80,000.
In
the end, through the use of a part-time weekend workforce and an
aggressive customized recruiting plan, Private Label Workforce
was able to achieve both objectives under tight time constraints.
Hiring
Right | Managing Growth | Controlling
Costs | Cutting Expenses
|